Review of tender documents for PHARE projects in the field of Environment, Slovenia
Review of tender documents for PHARE projects in the field of Environment, Slovenia

CATEGORY: Environment

LOCATION: Slovenia

START/END: 2003

CLIENT: European Commission

ORIGIN OF FUNDING: PHARE

Review of tender documents for PHARE projects in the field of Environment, Slovenia

Type of Services

The consultant undertook the following tasks:
- revision of the full set of tender documentation;
- recommendation of changes wherever necessary so as the objectives set previously were met;
- participation in the opening and evaluation sessions and provision of information regarding the procedure and application of the approved Tender Dossier.

Description

The main objective of this project was to assist the EC Delegation in Slovenia to revise the tender dossiers for the following four investment projects:
1. Construction of WWTP and Sewage System Kanal (total budget: 1,020,438 euros);
2. Ecological rehabilitation of the Idrijca river (total budget: 1,459,026 euros);
3. Construction of WWTP and corresponding Sewage System (total budget: 696,491 euros);
4. The waste water treatment plant and the Volce Sewerage system (total budget: 1,055,458 euros).
The role of the consultant was to ensure that the following objectives were achieved:
- the tender documentations are complete and comply with FIDIC Conditions of Contract and PHARE public procurement rules;
- the equipment to be procured comply with the Aquis Communautaire requirements and standards;
- the technical specifications and solutions are reasonable, clear and consistent, and ensure that the tenderers can effectively bill the supplies;
- the bill of quantities and drawings are clear and consistent;
- the estimation of costs for works and supplies are reasonable.
During the opening and evaluation sessions the consultant was the observer for the eight works tenders.