News


CATEGORY: Engineering & project management
LOCATION: Greece
START/END: 2011 - 2012
CONSULTANCY BUDGET: 808,594
CLIENT: Municipality of Orchomenos / Central Greece
ORIGIN OF FUNDING: National funds
PARTNERS: HYDROMENT S.A.
LDK’s BUDGET SHARE: 9,5%
STAFF PROVIDED: 3

Type of Services
LDK has the overall project management for the Electro-Mechanical Design Study. Specifically, LDK participated in the following:
- Electro-Mechanical Pre-Final Design Study for the WWTP (A’ PHASE)
- Electro-Mechanical Pre-Final and Detailed Design Study for the Sewage Network (Pumping Stations) (B’ PHASE).
Description
- PHASE A: Pre-Final Design Study with the following design parameters: Design population: 51,100p.e., Design Discharge: 8176 m3/d, Treatment Process: Secondary Treatment with Advance MRB system, that includes a prolonged aeration unit and filtration unit with membranes
- PHASE B: Pre – Final and Detailed Design Study of the sewage network of Dilessi and Plaka Dilessi settlements with the following elements: (a) Service area: 700ha, (b) Service Population: 26100, (c) Total Length of the internal network: 200km, (d) Pumping Stations: 4, (e) Total length of transfer pipes: 9.3km, (f) Pumping Stations of the Transfer System: 5.
- PHASE C: Topography Study.
- PHASE D: Geotechnical Design Study.
- PHASE E: Environmental Impact Assessment Study.
- PHASE F: Issuing of Tender Documents for Construction.